Thermite
Welding
ASRS, AGV, Activ, WMS
Retrotech Thermite Welding: Reasonable
Solutions to AS/RS Challenges. Quality is the foundation
of the products and services provided by Retrotech.
Retrotech’s phased installation
approach minimizes disruption of plant operations.
- Preliminary
Evaluation: Our engineer is dispatched to the site to
evaluate the existing rail design and current
condition. Detailed project designs are prepared and
submitted to the customer for approval. All materials are
ordered
based on the customer-approved Bills of Materials.
- Project
Preparation: The existing aisle floor is surveyed. Elevations
at the pad locations are measured with a laser
optical system. From the data, our engineers calculate
the quantity and thickness of additional shim packs
required for each location. This validates the correct
positioning
of the rail to the rack for proper storage and retrieval
of loads.
- Thermite welding process: The rail joints
are thermite welded. As part of the preparation, sections
of engineered
rails are matched, assembled, and clamped in place
with the extrusion profile direction matched to assure
joint
continuity.
Careful preheating and post heating of the joints
is done to assure joint continuity. Careful preheating
and post
heating of the joints is done to assure maximum joint
integrity. Upon completion of the weld, the rail
is precision ground
in the area of fusion to assure correct rail contour.
- Retrofit
installation- All of the old hardware and rail is removed.
New rails are installed. New
anchor bolt holes
are template-drilled and vacuumed to remove all
concrete dust prior to installation of new Grade 5 epoxy
anchors.
New shims are installed as specified by the engineer
to provide
optimum elevation.
- Rail Alignment and Adjustment:
A final laser alignment and clamping of the rail is made
and
hold-down nuts
are firmly torqued. A visible beam, rotating
beacon laser transit
is
used to provide highly accurate rail alignment
based on pre-established reference points. Aisle
measurements
are
taken in two-foot
increments to assure that the rail is in near
perfect alignment-epoxy grouting if required is infused
at this point. Any crane
wheel alignment problems are identified.
- Review,
Approval, and Thermite Welding Service: Customers review
and approve all installations.
Support documentation
is provided to assure customer awareness of
proper maintenance procedures for an extended rail life.
The Thermite Welding Process:
Uses high temperature chemical
reaction to heat rail joints to their fusion point, assuring
a complete joint weld.
Precision grinding of finished welds assures correct rail
contour.
Creates a continuous rail for the entire length of the aisle.
Eliminates excessive shock load damage to electrical and
mechanical assemblies due to poor rail joint welds and severe
wheel-to-rail impacts.
Results in a finished installation with the same hardness
and material characteristics as the parent rail.
High- impact epoxy grout under the crane rails.
Provides
continuous rail support.
Eliminates rail deflection
Prevents anchor pullout and rail creep.
The benefits of Retrotech AS/RS
Thermite Welding Crane Rail Replacements:
Less equipment
downtime
No open or worn rail joints
Reduced
anchor-bolt breakage
Smoother crane operation
Reduced crane component damage and load shifting due to jarring.
Longer rail and wheel life.
|